About The Project
This project will consist of the construction of sidewalks; installation of high visibility crosswalks and bike lane markings; installation of pedestrian delineators; and installation of ADA curb ramps.
Project Benefits
- Improved safety and accessibility for pedestrians
Timeline
- Construction: June 2026
- Completion: August 2026
Funding
This project is funded through a $482,977.00 Colorado Department of Transportation “Safe Routes to School” (SRTS) grant.
Advertisement Date
February 17, 2026
Scope of Work
- Replace damaged concrete sidewalk
- Install curb ramps
- Install bump out curb ramps on 10th Street to improve safety
- Install new traffic striping including bike lanes, buffer zones, crosswalks and reflective delineators along Monument Ave from 7th Street to 12th Street